Job Specifics: 
      Linestop® 48” SCCP Steel pipe / Actually 54” SCCP/ 56.9” Concrete 
      2 – 54” Linestop fittings 
      2 – Removal of pipe coating & Welding of assembly 
      2 – Insertion of 48” linestops on water for up to 7 days 
      2 – 4” Taps for blow down (If Needed) 
      2 – Removal of Linestop and install completion plug and cap 
       
      4” Bypass outlets off of Linestop machinery for your bypass installation. 
       
        ** Changed Condition** 
        Larger Linestop Fittings 
        Additional Pipe stripping 
        Additional Welding 
        Special 4” Liner thickness to prep for pilot drill 
         
        Linestop® 30” SCCP Steel pipe / 31.97” Steel O.D. / Concrete 34.22” 
        2 – 30” Linestop fitting 
        2 – Removal of pipe coating & Welding of assembly 
        2 – Insertion of 30” linestops on water for up to 7 days 
        2 – 2” – 4” Taps for blow down (If Needed) 
        2 – Removal of Linestops and install completion plugs and caps 
      4” Bypass outlets off of Linestop machinery for your bypass installation.
  |